CINTEC NORTH AMERICA ANNOUNCES RESTORATION WORK ON THE RED HOUSE, ALSO KNOWN AS THE SEAT OF PARLIAMENT FOR THE REPUBLIC OF TRINIDAD AND TOBAGO.
North American firm helps complete restoration of historic Trinidad building
Cintec North America has undertaken vital restoration work on The Red House, also known as the seat of Parliament for the Republic of Trinidad and Tobago.
The landmark $1m project marks a monumental moment in the history of structural engineering as one of the Reinforcement anchors inserted into the structure is believed to be the longest in the world, measuring 36.52 meters [ 120 Ft ] in the length. It was also the first time that Cintec had used 3D printing for sacrificial parts.
The original structure, built between 1844 and 1892, failed to reach its completion before it was severely damaged by a fire in March 1903, resulting in the start of the initial refurbishment in 1904.
Both the Beaux-Arts style architecture and red paint are key characteristics of the striking building.
In 2007, following Cintecs successful reinforcement of the Queens Royal Colleges external walls, Cintecs North American division was asked to advise Genivar, Engineers, (also known as W.S.P) and C.E.P on The Red Houses required repairs.
After lengthy discussions with Genivar and having an already triumphant track record in strengthening many of the worlds prestigious landmarks such as the White House and the Egyptian Pyramids, Cintec subsequently began working on The Red House in 2017.
Cintecs approved contractor, Celtest of Bangor (located in North Wales), was awarded the contract to install the Cintec Reinforcement System, under the guidance of project manager Jason Chinery.
Cintec provided additional specialist training and long reinforcements bars to Celest to ensure there would be no long hole drilling issues during the restoration.
During trials, it was calculated that the positioning of the drill would be deliberately pointing upwards at 0.50 degrees.
This would compensate for the force of gravity pulling down the core barrel, which was over 38m/125 ft in length, and proved extremely effective.
Robert Lloyd-Rees, managing director of Cintec North America, said: "Accuracy is critical during a project such as this, misalignment by one degree would mean the drill exiting at the wrong point causing a great deal of damage to the structure.
"We spent a great deal of time and used all of our own unique techniques to ensure that the project would be completely successful in restoring such an historic structure to its former glory."
Peter James, Cintec Group chairman, said: "This exciting project, with all of its technical difficulties, illustrates how our anchoring system can be adapted to solve the most complicated structural repairs in order to help restore yet another world-famous landmark.
###
About CINTEC
CINTEC North America is a world leader in the field of structural masonry retrofit strengthening, repair, and preservation. The principal activity of the company is the design and manufacture of the CINTEC Reinforcing Anchor System, a micro cement anchoring and reinforcing technique. CINTEC offers complete structural analysis and design services, turnkey solutions, as well as masonry repair and reinforcement anchors used for blast protection, seismic reinforcement, historic preservation and overall building strengthening. CINTEC has worked on projects around the world including the Egyptian Pyramids, Windsor Castle, Buckingham Palace, Statue of Liberty, the Library of Parliament in Canada and the White House.
CINTEC America of Baltimore, MD, has associated offices in Newport, Wales, UK; Newcastle, Australia; Ottawa, Canada and India.
For more information, call 1-800-363-6066; fax: 1 800.461.1862; e-mail: solutions@CINTEC.com or visit www.CINTEC.com.
###
Featured Product

T.J. Davies' Retention Knobs
Our retention knobs are manufactured above international standards or to machine builder specifications. Retention knobs are manufactured utilizing AMS-6274/AISI-8620 alloy steel drawn in the United States. Threads are single-pointed on our lathes while manufacturing all other retention knob features to ensure high concentricity. Our process ensures that our threads are balanced (lead in/lead out at 180 degrees.) Each retention knob is carburized (hardened) to 58-62HRC, and case depth is .020-.030. Core hardness 40HRC. Each retention knob is coated utilizing a hot black oxide coating to military specifications. Our retention knobs are 100% covered in black oxide to prevent rust. All retention knob surfaces (not just mating surfaces) have a precision finish of 32 RMA micro or better: ISO grade 6N. Each retention knob is magnetic particle tested and tested at 2.5 times the pulling force of the drawbar. Certifications are maintained for each step in the manufacturing process for traceability.